DeliveryUnknownsources checked 26 Oct 2026

The line was energised on 8 August 2026, and a 5 MW import was used to test and commission the commercial metering. At the start of September, commercial trade was still waiting on a tariff. No source read shows the line in service after the tests, so the delivery status stays unknown.

  • line energised · 8 Aug 2026
    "transmission line from Matambo Substation in Mozambique to Phombeya Substation in Malawi energised on August 8 2026" "transmission line from Matambo Substation in Mozambique to Phombeya Substation in Malawi energised on August 8 2026"Malawi-Mozambique power line passes test · article text · 8 Aug 2026not yet checked by a personSecondary source: no EDM, ESCOM or Malawi ministry statement was found
    Malawi-Mozambique power line passes test · article text · not yet checked by a person
  • test transfer of 5 MW · undated
    "Malawi and Mozambique Power Interconnector went live on test basis with a transfer of five megawatts"; the import was "symbolic to test and commission commercial metering equipment" "Malawi and Mozambique Power Interconnector went live on test basis with a transfer of five megawatts"; the import was "symbolic to test and commission commercial metering equipment"Malawi-Mozambique power line passes test · article textnot yet checked by a personSecondary source: no EDM, ESCOM or Malawi ministry statement was found
    Malawi-Mozambique power line passes test · article text · not yet checked by a person
  • commercial trade pending a tariff
    "is currently finalising discussions on the tariff and other arrangements required" "is currently finalising discussions on the tariff and other arrangements required"Malawi-Mozambique power line passes test · article text, attributed to the Ministry of Energy; report of 1 September 2026not yet checked by a personSecondary source: no Malawi ministry statement was found
    Malawi-Mozambique power line passes test · article text, attributed to the Ministry of Energy; report of 1 September 2026 · not yet checked by a person
  • commissioning (date as reported) · 10 Aug 2026
    "the 218-km Mozambique–Malawi transmission interconnector, which was commissioned on August 10, 2026" "the 218-km Mozambique–Malawi transmission interconnector, which was commissioned on August 10, 2026"Malawi–Mozambique interconnector commissioned after construction delays · first paragraph · 10 Aug 2026not yet checked by a personSecondary source: no EDM or ESCOM statement was found
    Malawi–Mozambique interconnector commissioned after construction delays · first paragraph · not yet checked by a person
Sources disagree

Nyasa Times (20 August 2026) reported that Malawi's end-of-July deadline had passed with no power yet flowing into Malawi (its wording is in the evidence below), twelve days after the energisation date that The Nation later gave and ten days after Global Transmission's commissioning date. The reports may use "flowing" for commercial supply rather than a test transfer, but none says so.

Not established
  • Whether a tariff has been agreed and commercial supply has begun. The Nation's report of 1 September 2026 is the latest found.
  • How much power will be traded over the line, and on what contract terms.
FundingUnknownsources checked 26 Oct 2026
Not established
  • Who financed the line and on what terms. No financing document was read.

Evidence

  • Statement
    "has passed without a single megawatt flowing into Malawi." "has passed without a single megawatt flowing into Malawi."Malawi's Power Crisis Deepens As Mozambique Lifeline Misses Third Deadline · article textnot yet checked by a personSecondary source: no ESCOM or Malawi ministry statement was found
    Malawi's Power Crisis Deepens As Mozambique Lifeline Misses Third Deadline · article text · not yet checked by a person

Institutions named

A role is shown only where a quoted source says what the institution does on this reform.

Reach: 0 cross-border links, 0 blockers, 2 institutions in 2 countries or bodies. Counted from the records.