Project · Zimbabwe, Zambia, Botswana, Namibia
ZiZaBoNa interconnector (Zimbabwe-Zambia component first)
Record SAPP-P-0001 · draft, not yet reviewed by a person
Status by track
DeliveryUnknown · target 2026sources checked 16 Oct 2026
- construction start · target: 2026"Construction is scheduled to begin in 2026, with commercial operations anticipated from 2028." "Construction is scheduled to begin in 2026, with commercial operations anticipated from 2028."not yet checked by a personElectricity wheeling could unlock regional power trade in Southern Africa · article text · not yet checked by a person
- expected effect (SAPP's statement)"This is expected to relieve transmission congestion in the central corridor." "This is expected to relieve transmission congestion in the central corridor."wording checked against the documentSAPP Quarterly Report, October to December 2025 · p.8 (PDF page; printed page may differ) · wording checked against the document
- latest project stage in PIDA's database · 2019"S3B: Transaction Support & Financial Close (2019)" "S3B: Transaction Support & Financial Close (2019)"not yet checked by a personZiZaBoNa Transmission Project, PIDA project database entry · project page, stage field (page carries no update date) · not yet checked by a person
Not established
- Construction status and financial close. PIDA's database leaves construction dates blank, and no financial close or construction start was found on SAPP's pages on 16 October 2026.
- How much of the untraded energy in SAPP-K-0001 it would relieve. No source quantifies this.
FundingUnknownsources checked 16 Oct 2026
- finance mobilisation (consultation) · 17 Dec 2025SAPP and ZESA held a technical consultative meeting on 17 December 2025 "to explore readiness to mobilise financial resources and accelerate investment" SAPP and ZESA held a technical consultative meeting on 17 December 2025 "to explore readiness to mobilise financial resources and accelerate investment"wording checked against the documentSAPP Quarterly Report, October to December 2025 · p.7 (PDF page; printed page may differ) · wording checked against the document
Blockers
- Central-corridor transmission limits leave matched energy untraded · expected to relieve it
Connections
- Joint action or dependency with New wholesale market (SAWEM), Open access to the networks, Untraded matched energy, NamPower outages
Institutions named
A role is shown only where a quoted source says what the institution does on this reform.
Reach: 1 cross-border links, 1 blockers, 3 institutions in 3 countries or bodies. Counted from the records.