Programme · South Africa
Independent Transmission Projects programme, phase I
Record ZAF-R-0002 · draft, not yet reviewed by a person
Status by track
LegalUnknown
Not established
- No source on the legal basis was read.
DeliveryTargeted · 2026, Q2 2027sources checked 10 Oct 2026
- procurement, second draft RFP to the seven pre-qualified bidders · target: before the end of 2026a second draft RFP goes to "the seven ITP PQBs" before the end of 2026 a second draft RFP goes to "the seven ITP PQBs" before the end of 2026paraphrase, not a quotationUpdate on Independent Transmission Projects programme · article text · paraphrase, not a quotation
- procurement, final RFP release · target: Q2 2027"The final RFP is targeted for release in quarter 2 of the 2027 calendar year." "The final RFP is targeted for release in quarter 2 of the 2027 calendar year."wording checked against the documentUpdate on Independent Transmission Projects programme · article text · wording checked against the document
Not established
- No construction start or timeline in the sources read. Phase I is "approximately 1164 kilometres of new transmission infrastructure".
- Whether any phase I line would raise South Africa's import or export capacity toward SAPP.
FundingTargeted · Q1 2027sources checked 10 Oct 2026
- Credit Guarantee Vehicle incorporated · 12 Aug 2026"The CGV was registered and incorporated on 12 August 2026." "The CGV was registered and incorporated on 12 August 2026."wording checked against the documentUpdate on Independent Transmission Projects programme · article text · wording checked against the document
- binding CGV term sheet · target: by the end of the first quarter of 2027"a binding CGV term sheet by the end of the first quarter of 2027" "a binding CGV term sheet by the end of the first quarter of 2027"wording checked against the documentUpdate on Independent Transmission Projects programme · article text · wording checked against the document
Not established
- Rand value of the CGV capitalisation.
Institutions named
A role is shown only where a quoted source says what the institution does on this reform.
- Development Bank of Southern Africa
- National Transmission Company South Africa
- Department of Electricity and Energy
- National Treasury
Reach: 0 cross-border links, 0 blockers, 4 institutions in 1 country. Counted from the records.
In SA Policy Space
SA Policy Space records this reform as "under_review". That single label is kept as source information; the tracks above say what the evidence here supports. Open it in SA Policy Space