Project · Botswana, Zambia

Kazungula bridge and one-stop border post (Botswana and Zambia)

Record ZMB-P-0001 · draft, not yet reviewed by a person

Cite as: Laurence Wilse-Samson, Bridging African Borders, record ZMB-P-0001: "Kazungula bridge and border post" (public draft, built 2026-11-01). https://borders.lwilsesamson.com/ideas/zmb-p-0001/ Data and citation

Status by track

DeliveryOperating · 10 May 2021sources checked 30 Oct 2026

The bridge over the Zambezi and the one-stop border post facilities linking Botswana and Zambia were commissioned on 10 May 2021. They replaced a pontoon ferry.

  • bridge and one-stop border post commissioned · 10 May 2021
    "The US$259 million Kazungula Bridge over the Zambezi River and One Stop Border Post facilities connecting Botswana and Zambia were commissioned on 10th May 2021" "The US$259 million Kazungula Bridge over the Zambezi River and One Stop Border Post facilities connecting Botswana and Zambia were commissioned on 10th May 2021"US$259m Kazungula Bridge and One Stop Border Post Commissioned, Paving way for Enhanced SADC Integration and Development · news item text, first paragraph · 10 May 2021wording checked against the documentChecked by Laurence Wilse-Samson, 1 Nov 2026, against the document (after a machine match on the runner text)
    US$259m Kazungula Bridge and One Stop Border Post Commissioned, Paving way for Enhanced SADC Integration and Development · news item text, first paragraph · wording checked against the document
Not established
  • The legal instrument under which Botswana and Zambia run the post as one stop. No bilateral agreement was read.
  • Clearance or crossing times after 2022. Not found in the sources read.
FundingUnknown
Not established
  • How the cost was shared between the two governments, the African Development Bank and JICA, and on what terms. The SADC item names the funders (cited at record level) but gives no shares.

Financing

What the sources say this costs and who is putting money in. All projects' financing

Stated amountWhat it measuresCoversPrice basisSource
USD 259 millionproject costthe Kazungula bridge and the one-stop border post facilitiesnot stated by the source; financing costs included: not stated by the source"The US$259 million Kazungula Bridge over the Zambezi River and One Stop Border Post facilities connecting Botswana and Zambia"US$259m Kazungula Bridge and One Stop Border Post Commissioned, Paving way for Enhanced SADC Integration and Development · news item text, first paragraphwording checked against the documentChecked by Laurence Wilse-Samson, 1 Nov 2026, against the document (after a machine match on the runner text)
about BWP 1,994.95 millioncontract valuepackage one, the bridge and approach rampsnot stated by the source; financing costs included: not stated by the source"the bridge, whose construction commenced in 2014 at a contract sum of approximately P1 994 950 041.44 (USD174 184 799.54) was 100 per cent complete"Kazungula bridge complete · article textwording checked against the documentChecked by Laurence Wilse-Samson, 1 Nov 2026, against the document (after a machine match on the runner text)Secondary source: the Ministry of Transport and Communications' release was not found
BWP 440.116 millioncontract valuepackage two, the Botswana one-stop border postnot stated by the source; financing costs included: not stated by the source"package two, being a Botswana one stop border post, currently under construction at a cost of P440 116 275.30"Kazungula bridge complete · article textwording checked against the documentChecked by Laurence Wilse-Samson, 1 Nov 2026, against the document (after a machine match on the runner text)Secondary source: the Ministry of Transport and Communications' release was not found
about BWP 150.442 millioncontract valuepackage three, the Zambia one-stop border postnot stated by the source; financing costs included: not stated by the source"Package three, the Zambia one stop border post, ongoing at a contract sum of about P150 441 669.48 (ZMW 263 670 419.98)"Kazungula bridge complete · article textwording checked against the documentChecked by Laurence Wilse-Samson, 1 Nov 2026, against the document (after a machine match on the runner text)Secondary source: the Ministry of Transport and Communications' release was not found
Not established
  • The three contract sums total about 2.59 billion pula. SADC's US$259 million is not reconciled with them; the sources give no exchange rate or common date.
  • The dollar and kwacha figures in the Botswana report are its own conversions; they are kept in the quotes and not used as figures.

Sources checked 30 Oct 2026. Amounts are shown in the currency the source gives, never converted or added together.

Observations

Two figures only: cargo clearance time at the Kazungula one-stop border post before the JICA project and in a 2022 survey, as a JICA news item reports them. The earlier period is not stated and the survey report was not read.

PeriodSegmentMeasureValueDenominatorSource
not stated by the source (before JICA's project)cargoclearance time30 hoursnot defined by the source (whether an average, and which steps are included, is not stated)"the clearance time for cargo at Kazungula OSBP, which is located at the border of Zambia and Botswana, has been highly reduced from 30 hours to 12 hours, approximately one third"Clearance Time Reduced to One Third at the Critical Border Post in Zambia · news item textwording checked against the documentChecked by Laurence Wilse-Samson, 1 Nov 2026, against the document (after a machine match on the runner text)
2022cargoclearance time12 hoursnot defined by the source (whether an average, and which steps are included, is not stated)"In 2022, a survey on the progress of the Project was conducted"; "the clearance time for cargo at Kazungula OSBP, which is located at the border of Zambia and Botswana, has been highly reduced from 30 hours to 12 hours, approximately one third"Clearance Time Reduced to One Third at the Critical Border Post in Zambia · news item textwording checked against the documentChecked by Laurence Wilse-Samson, 1 Nov 2026, against the document (after a machine match on the runner text)
How to read these figures
  • JICA calls the fall "approximately one third", and its headline says clearance time was reduced to one third; 12 hours is 40% of 30. The item also says cargo vehicles "still take several hours to cross" and that the pre-clearance option is not fully used.

Evidence

  • who designed, built and funded it
    "detailed designs and construction were jointly led and coordinated by the Governments of Botswana and Zambia, and funded by the two Governments, supported by the African Development Bank and the Japan International Cooperation Agency (JICA)" "detailed designs and construction were jointly led and coordinated by the Governments of Botswana and Zambia, and funded by the two Governments, supported by the African Development Bank and the Japan International Cooperation Agency (JICA)"US$259m Kazungula Bridge and One Stop Border Post Commissioned, Paving way for Enhanced SADC Integration and Development · news item text, SADC Executive Secretary's remarkswording checked against the documentChecked by Laurence Wilse-Samson, 1 Nov 2026, against the document (after a machine match on the runner text)
    US$259m Kazungula Bridge and One Stop Border Post Commissioned, Paving way for Enhanced SADC Integration and Development · news item text, SADC Executive Secretary's remarks · wording checked against the document
  • expected effect on Beitbridge (Mozambique's President, as reported)
    "He further said the bridge offers a faster alternative route to Beitbridge and will help alleviate the congestion at one of Africa’s busiest borders" "He further said the bridge offers a faster alternative route to Beitbridge and will help alleviate the congestion at one of Africa’s busiest borders"US$259m Kazungula Bridge and One Stop Border Post Commissioned, Paving way for Enhanced SADC Integration and Development · news item textwording checked against the documentChecked by Laurence Wilse-Samson, 1 Nov 2026, against the document (after a machine match on the runner text)
    US$259m Kazungula Bridge and One Stop Border Post Commissioned, Paving way for Enhanced SADC Integration and Development · news item text · wording checked against the document
Still unknown
  • How much traffic the bridge carries, and whether any has moved from Beitbridge. Not found in the sources read.